EMoreShare

Case Study: 100kWh Energy Storage System Delivers 18% IRR in Italy

This detailed case study examines a real-world commercial energy storage installation completed by EMoreShare in Northern Italy. The project demonstrates how a properly sized and implemented battery system can deliver exceptional financial returns while providing operational benefits to a mid-sized manufacturing facility.

With an achieved IRR of 18% and a payback period under 6 years, this installation serves as a benchmark for similar facilities across Italy and Southern Europe considering energy storage investments.

18%
Project IRR
5.8 yrs
Payback Period
€68,400
Annual Savings
€397k
20-Year NPV

Client Background

Company Profile

Attribute Details
Industry Precision metal fabrication
Location Modena, Emilia-Romagna, Italy
Facility Size 8,500 m² manufacturing + 2,000 m² warehouse
Employees 85 (2 shifts)
Annual Revenue €12 million

The client, a family-owned business operating since 1987, produces precision-machined components for the automotive and aerospace industries. Their customer base includes major Tier-1 suppliers to Ferrari, Lamborghini, and Maserati, requiring consistent quality and on-time delivery.

Energy Profile (Pre-Installation)

Parameter Value
Annual Electricity Consumption 1,450 MWh
Contracted Power 600 kW
Peak Demand (12-month average) 485 kW
Maximum Recorded Peak 542 kW
Annual Electricity Cost €198,000
Average Cost per kWh €0.137

The facility operated on a medium-voltage industrial tariff with time-of-use pricing. Demand charges represented 38% of the total electricity bill—a significant pain point for the operations team.

Needs Analysis and Project Objectives

Initial Consultation

EMoreShare's engineering team conducted a comprehensive site assessment in March 2025, including:

Key Challenges Identified

  1. High demand charges: €19.50/kW/month creating €113,000 annual cost burden
  2. Peak demand volatility: CNC machines and welding equipment creating unpredictable 50-100 kW demand spikes
  3. Power quality issues: Voltage sags during machine startup affecting sensitive equipment
  4. Limited grid capacity: Constrained ability to add new equipment without expensive grid upgrades
  5. Sustainability goals: Customer pressure to reduce carbon footprint

Project Objectives

The client established the following priorities:

Priority Objective Target
1 Reduce peak demand charges 30% reduction minimum
2 Improve power quality Eliminate voltage sags
3 Enable future expansion Defer grid upgrade
4 Achieve positive ROI Payback under 7 years
5 Minimize operational disruption Installation during planned shutdown

System Design and Specification

Sizing Analysis

Based on detailed load analysis, EMoreShare engineers determined optimal system sizing:

Peak Shaving Analysis:
Current peak: 542 kW
Target peak: 380 kW (30% reduction)
Required peak reduction: 162 kW
Average peak duration: 2.8 hours
Required energy capacity: 162 kW × 2.8 h × 1.2 (safety) = 544 kWh
With 90% DoD: 605 kWh nominal → Specified 600 kWh

However, the client had budget constraints that made a 600 kWh system challenging. EMoreShare proposed a phased approach:

Final System Specification

Component Specification
Battery Technology Lithium Iron Phosphate (LFP)
Nominal Capacity 215 kWh (usable: 194 kWh at 90% DoD)
Power Rating 100 kW continuous / 120 kW peak (10 min)
AC-DC Efficiency 94% round-trip
Enclosure IP54 outdoor-rated container
Dimensions 2.4m × 1.2m × 2.1m (H)
Weight 2,800 kg
Fire Suppression Aerosol-based with gas detection
Thermal Management Active cooling, -10°C to +45°C operation
Expected Cycle Life 8,000 cycles (80% capacity retention)
Warranty 10 years / 70% capacity

Control System

The EMoreShare EMS (Energy Management System) provides:

Installation Process

Project Timeline

Phase Duration Activities
Contract Signing Week 0 Deposit payment, final design approval
Permitting Weeks 1-4 Grid connection application, fire authority notification
Manufacturing Weeks 2-8 System build and factory testing
Site Preparation Weeks 6-9 Foundation, electrical infrastructure
Delivery & Installation Week 10 System delivery, mechanical installation
Commissioning Weeks 10-11 Electrical connection, testing, grid approval
Training & Handover Week 12 Operator training, documentation, go-live

Installation Details

Site Preparation:

Grid Connection:

Challenges Encountered:

First-Year Operation Data

Performance Metrics

The system entered commercial operation on July 15, 2025. Twelve-month performance data:

Metric Value
System Availability 99.2%
Total Cycles Completed 312
Average Daily Cycles 0.85
Average Discharge Depth 73%
Round-trip Efficiency (measured) 92.8%
Capacity Retention (Year 1) 99.1%
Unplanned Downtime 18 hours (software update)

Peak Shaving Results

Month Pre-System Peak (kW) Post-System Peak (kW) Reduction (kW) Reduction %
Jul 2025 538 442 96 17.8%
Aug 2025 545 438 107 19.6%
Sep 2025 521 425 96 18.4%
Oct 2025 512 418 94 18.4%
Nov 2025 528 431 97 18.4%
Dec 2025 518 421 97 18.7%
Jan 2026 535 436 99 18.5%
Feb 2026 522 428 94 18.0%
Mar 2026 541 445 96 17.7%
Apr 2026 519 423 96 18.5%
May 2026 532 438 94 17.7%
Jun 2026 548 451 97 17.7%
Average 530 433 97 18.3%

Financial Performance

Revenue/Savings Category Annual Amount (€) % of Total
Demand charge reduction 22,698 33.2%
Energy arbitrage (TOU optimization) 18,450 27.0%
Power factor correction 4,200 6.1%
Deferred grid upgrade 15,000 21.9%
Power quality improvement (avoided downtime) 8,052 11.8%
Total Annual Benefit 68,400 100%

IRR Calculation and Financial Analysis

Project Costs

Cost Category Amount (€)
Battery system (215 kWh) 280,000
Inverter and BOS 42,000
Installation labor 28,000
Grid connection and permits 15,000
Engineering and project management 18,000
Site preparation (foundation, electrical) 22,000
Total Project Cost 405,000

Financial Model Assumptions

Parameter Value
Analysis Period 20 years
Discount Rate 7%
Electricity Price Escalation 3% annually
Battery Degradation 2% annually (years 1-5), 1.5% (years 6-10), 1% (years 11-20)
Operating Costs €3,500/year (maintenance, insurance, monitoring)
Inverter Replacement Year 12 (€35,000)
Tax Rate 24% (Italy corporate tax)
Tax Depreciation 9% annually (Italian industrial equipment)

Key Financial Metrics

Metric Value
Simple Payback 5.8 years
Discounted Payback 7.2 years
Internal Rate of Return (IRR) 18.0%
Net Present Value (NPV) €397,000
Benefit-Cost Ratio 2.84
Levelized Cost of Storage (LCOS) €0.089/kWh

Sensitivity Analysis

Scenario IRR Payback
Base Case 18.0% 5.8 years
Electricity prices +20% 22.4% 4.6 years
Electricity prices -20% 13.2% 7.8 years
System cost +15% 14.8% 6.9 years
System cost -15% 22.1% 4.7 years
Degradation 50% faster 16.2% 6.4 years

Lessons Learned and Best Practices

What Worked Well

  1. Thorough pre-installation monitoring: The 6-month monitoring period allowed precise sizing and accurate savings projections
  2. Phased approach: Starting with a smaller system reduced upfront risk and demonstrated value before larger commitment
  3. Integration with existing systems: BMS integration provided operational insights beyond energy savings
  4. Operator training: Well-trained facility staff resolved minor issues without service calls
  5. Remote monitoring: EMoreShare's 24/7 monitoring caught and resolved one potential issue before it affected operations

Challenges and Solutions

Challenge Impact Solution
Summer heat wave (Aug 2025) Reduced battery efficiency by 3% Adjusted thermal management setpoints; efficiency recovered
Grid voltage fluctuations 3 brief disconnections Adjusted protection settings; no issues since
Unexpected production surge Peak exceeded target twice Adjusted prediction algorithm; improved forecasting accuracy

Recommendations for Similar Projects

  1. Invest in monitoring: At least 6 months of interval data significantly improves sizing accuracy
  2. Plan for expansion: Even if starting small, design infrastructure for future growth
  3. Consider power quality: The voltage regulation benefits, while hard to quantify, provide real operational value
  4. Engage operators early: Facility staff who understand the system become advocates for expansion
  5. Document everything: Detailed records of performance support financing for Phase 2

Frequently Asked Questions

Q: Why did you choose 200 kWh instead of the calculated 600 kWh?

A: The client had budget constraints and wanted to validate the technology before a larger investment. The 200 kWh system delivers meaningful savings (18% peak reduction) while demonstrating operational benefits. Phase 2 expansion to 400 kWh is planned for 2027, with final 600 kWh configuration by 2028.

Q: How much maintenance does the system require?

A: Very little. The system receives quarterly preventive maintenance visits (4 hours each) and continuous remote monitoring. The client performs monthly visual inspections. Total annual maintenance cost is approximately €3,500 including service contract.

Q: Has the system experienced any safety issues?

A: No safety incidents have occurred. The LFP battery chemistry is inherently safer than other lithium-ion types, and the multi-layer protection system (cell, module, system) has operated flawlessly. One thermal alarm triggered during the August heat wave, but the cooling system responded appropriately.

Q: How has this affected the client's operations?

A: The impact has been entirely positive. The system operates automatically without any operator intervention. Power quality improvements have reduced nuisance trips on sensitive CNC equipment. The client reports improved confidence in adding new equipment without grid concerns.

Q: Would you recommend this approach to other manufacturers?

A: Absolutely, with caveats. Facilities with high demand charges, volatile loads, and limited grid capacity are ideal candidates. The phased approach reduces risk but requires discipline to follow through with expansions. For this client, the 18% IRR significantly exceeds their hurdle rate for capital investments.

Achieve Similar Results for Your Facility

This Italian manufacturing facility achieved an 18% IRR with their EMoreShare energy storage system. Your facility could see similar or better returns depending on your specific energy profile and tariff structure.

Contact EMoreShare today for a free site assessment and customized financial projection. Our team has delivered successful installations across Italy, the UK, and Spain.

Email: eason.yang@emoreshare.com | Phone: +86-XXX-XXXX-XXXX


Published: April 2026 | Last Updated: April 2026 | EMoreShare—Commercial Energy Storage Solutions for Europe